Unload window frames and glasses at respective locations of installation. Locations are given on the labels pasted on each frame.
Align the window frame in perfect vertical level in the opening. Check with a plumb bob and spirit level
Packing needs to be provided ALL AROUND the window frame. EVEN at the BOTTOM. GAP on all sides need to be uniform as far as possible.
All open drain holes and screw holes need to be filled in with proper color CAPS supplied with the windows.
Glass packers must be used on all FOUR sides of the window frame.
Then hardware alignment is done to get lock and other hardware in ideal working state.
INSIDE as well as OUTSIDE sealing is mandatory. When the gaps between the window frame and the wall exceed 10mm, baker rods must be used first to fill the gaps before applying the silicone sealant.
All garbage occurring as a result of unpacking and installation, needs to be collected and disposed off by the contractor after consultation with the Client Representative to a suitable location.
Joint inspection with client representative and handover of the site.